[All_jlau] Message from Hugh Montgomery - Schedule Notice

Mary Beth Stewart stewartm at jlab.org
Fri Sep 18 08:34:03 EDT 2015


/Sent on behalf of Hugh Montgomery/

Dear Colleagues,

Following discussions with Accelerator and Experimental Physics division 
leadership, and with information discussed at the recent Shutdown 
Oversight Board 2015 meetings, we have decided that the CEBAF 
accelerator operations will start on November 9, 2015.  The five weeks 
of beam operations  before the Winter break will be devoted to 
establishing a fully operational 12 GeV CEBAF;  measuring beam 
properties and establishing physics quality beams at design energy.

With input from 12GeV Project, the Chairs of the Scheduling Committee 
are developing a strawman schedule including experiments for the 2016 
“Spring” run.

Before it is finalized, potential negative impacts of the strawman will 
be scrutinized.

Regards, Mont
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/all_jlau/attachments/20150918/814c1b46/attachment.html>


More information about the All_jlau mailing list