Dear collaborators,<br><br>We have a lot to do today, and not enough people so please let us know if you can help out:<br>-- shift leaders for day shift (coming in before 10am is good enough) and owl shift<br>-- cabling help this afternoon (3-4 people).<br>
-- analysis experts during swing and owl shifts <br><br>In all cases, if you can help please email us or sign up on the wiki, **and** give us contact info so we can let you know if there are any changes of plans. <br><br>
A tentative schedule is below:<br>* Work on the corrector magnet power supply was finished late last night, so we hope to start the beamline commissioning tests around 10 or 11.<br>* After these tests, we'll get as much work done on the right arm as possible, and start cosmics and/or beam commissioning of HRS-R as soon as possible.<br>
<br>Thanks in advance!<br>Natalia Toro<br>