[Bteam] Tomorrow's agenda
Arne Freyberger
freyberg at jlab.org
Tue Aug 11 14:50:15 EDT 2009
B-team Meeting Agenda (2:00pm Wednesday MCC conf. room)
1 2009-08-12 Wed Agenda
* Parity Quality Beam/Injector Setup
o Pockel Cell Alignment Physics
o Injector setup Kazimi
Status and future plans
o Remaining Beam studies/injector work before physics
+ Yves PQB optimization Status and schedule
+ Matching into NL Schedule
* August Configuration
Hopefully I'll know what physics wants by tomorrow.... 2009-08-11
Tue 14:41
Just heard from Physics, they would like a 7.5% unbalanced setup.
During the Hall-A one-pass running the ?_Wien set such that B get
100% alignment.
Tuesday Aug. 25th Hall-A goes to 3-pass and ?_Wien set such that A
get 100% alignment.
o Startup plans Yan
Details of the startup presented for review.
* Fall beam studies
Discuss overall goals for Beam studies this fall. In terms of
support for the future program, a major chunk of beam studies will
be used for commissioning the C50-9 module. We will discuss other
major efforts for the fall as well to help prioritize the beam
studies scheduling.
2 2009-08-04 Tue 07:22 Updated startup schedule
Reminder there will not be a BTeam meeting this week. We will meet next
week. At Steve's Monday 1:30 meeting the remaining SAD work was
discussed. There are a few tasks that have an impact on Beam activities,
specifically C50-9 installation. As such here is the new schedule.
* Startup items
o C50-9 work implies the NL will be in restricted access
during weekdays up to Aug 13th. This will constrained the
Inj work to either 500keV or Swing/Owl shifts.
o Make sure Yves has enough time to perform measurements,
analysis and configuration changes.
o Tief needs a shift of RF on (no beam) to move the MO around
to examine the range of the tuners (12 GeV test)
o Emax's need to be determined for NL05, NL10, SL17, SL18
o NL05, NL10, SL17 & SL18 need to have parasitic Q
measurements performed once Emax's have been determined and
RF is stable.
o Once tune beam is in the BSY, BSY harps need to be checked
o tune beam to BSY, and BSY harps work: Perform BSY ?, TWISS
measurements and matching
* Aug09 startup
Date Owl Day Swing
2009-08-06 Thu C50-9 in tunnel
10:30 PSS lockup PSS Func. Tst
2009-08-07 Fri C50-9 inst & hookup C50-9 bake started
2009-08-08 Sat C50-9 bake terminated NL:PowerPermit
Final Leak check
NL:PowerPermit(13:00)
~13:00 Inj setup to 45MeV Inj setup to 45MeV
2009-08-09 Sun NL:PowerPermit NL:PowerPermit
Inj. setup to 45MeV Inj setup to 45 MeV
Inj parity checks(Yves?)
2009-08-10 Mon ops 24/7 NL:Restricted Access CEBAF:PowerPermit
Emax:2L17,2L18,1L05,1L10
Inj Parity checks Inj parity checks
up to 500keV(Yves?/HappexIII) up to 45 MeV(Yves?)
2009-08-11 Tue Power Permit:CEBAF NL: Restrct Acc.
Emax:2L17,2L18,1L05,1L10
RECO:Lauze SL: PP
C50-9 4k pumpdown
2009-08-12 Wed CEBAF:PowerPermit NL Restricted Access
CEBAF:PowerPermit
PD:YanWang SL Power Permit
C50-9 2K pumpdown
Heat/Reactivate Cathode? parasiticQ:1L05,1L10,2L17,2L18
2009-08-13 Thu CEBAF:PowerPermit CEBAF:PowerPermit
CEBAF:PowerPermit
parasiticQ:1L05,1L10,2L17,2L18 Inj to 45 MeV Inj to 45 MeV
Parity Quality (Yves) Parity Quality(Yves)
MO swing? (Tief) MO swing?(Tief)
parasiticQ:1L05,1L10,2L17,2L18
2009-08-14 Fri CEBAF:PowerPermit CEBAF:PowerPermit
CEBAF:PowerPermit
All systems ON Start beam recovery 5.9 GeV balanced setup
parasiticQ:1L05,1L10,2L17,2L18 5.9 GeV balanced setup
MO swing?(Tief)
2009-08-15 Sat CEBAF:PowerPermit CEBAF:PowerPermit
5.9GeV bal. setup 5.9GeV bal. setup ....
2009-08-16 Sun
.... .... ....
2009-08-17 Mon CEBAF:open if needed 5.76 GeV unbal. setup
... for repairs
5.76 GeV unbal. setup
2009-08-18 Tue 5.76GeV unbal. setup 5.76GeV unbal. setup
5.76GeV unbal. Beam
1/5/2 pass separation 1/5/2 separation
BSY Beam matching BSY Beam matching
2009-08-19 Wed 5.76GeV unbal. Beam Beam to Halls Beam to Halls
PD: Kazimi CW to BSY dump BSY Beam matching Energy Spread opt.
Parity quality checks
2009-08-20 Thu Beam to Halls Beam to Halls Beam to Halls
Energy Spread opt. Energy Spread opt. Energy Spread opt.
2009-08-21 Fri Beam to Halls Physics Physics
Date: 2009-08-11 14:49:11 EDT
HTML generated by org-mode 6.28e in emacs 22
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/bteam/attachments/20090811/c0a2b27f/attachment-0002.html>
More information about the BTeam
mailing list