[Bteam] Tomorrow's agenda

Arne Freyberger freyberg at jlab.org
Tue Aug 11 14:50:15 EDT 2009


  B-team Meeting Agenda (2:00pm Wednesday MCC conf. room)


    1 2009-08-12 Wed Agenda

    * Parity Quality Beam/Injector Setup
          o Pockel Cell Alignment Physics
          o Injector setup Kazimi
            Status and future plans
          o Remaining Beam studies/injector work before physics
                + Yves PQB optimization Status and schedule
                + Matching into NL Schedule
    * August Configuration
      Hopefully I'll know what physics wants by tomorrow.... 2009-08-11
      Tue 14:41
      Just heard from Physics, they would like a 7.5% unbalanced setup.
      During the Hall-A one-pass running the ?_Wien set such that B get
      100% alignment.

      Tuesday Aug. 25th Hall-A goes to 3-pass and ?_Wien set such that A
      get 100% alignment.

          o Startup plans Yan
            Details of the startup presented for review.
    * Fall beam studies
      Discuss overall goals for Beam studies this fall. In terms of
      support for the future program, a major chunk of beam studies will
      be used for commissioning the C50-9 module. We will discuss other
      major efforts for the fall as well to help prioritize the beam
      studies scheduling.


    2 2009-08-04 Tue 07:22 Updated startup schedule

Reminder there will not be a BTeam meeting this week. We will meet next 
week. At Steve's Monday 1:30 meeting the remaining SAD work was 
discussed. There are a few tasks that have an impact on Beam activities, 
specifically C50-9 installation. As such here is the new schedule.

    * Startup items
          o C50-9 work implies the NL will be in restricted access
            during weekdays up to Aug 13th. This will constrained the
            Inj work to either 500keV or Swing/Owl shifts.
          o Make sure Yves has enough time to perform measurements,
            analysis and configuration changes.
          o Tief needs a shift of RF on (no beam) to move the MO around
            to examine the range of the tuners (12 GeV test)
          o Emax's need to be determined for NL05, NL10, SL17, SL18
          o NL05, NL10, SL17 & SL18 need to have parasitic Q
            measurements performed once Emax's have been determined and
            RF is stable.
          o Once tune beam is in the BSY, BSY harps need to be checked
          o tune beam to BSY, and BSY harps work: Perform BSY ?, TWISS
            measurements and matching
    * Aug09 startup
      Date 	Owl 	Day 	Swing
      2009-08-06 Thu 		C50-9 in tunnel 	
      		10:30 PSS lockup 	PSS Func. Tst
      			
      2009-08-07 Fri 		C50-9 inst & hookup 	C50-9 bake started
      			
      2009-08-08 Sat 		C50-9 bake terminated 	NL:PowerPermit
      		Final Leak check 	
      		NL:PowerPermit(13:00) 	
      		~13:00 Inj setup to 45MeV 	Inj setup to 45MeV
      			
      2009-08-09 Sun 		NL:PowerPermit 	NL:PowerPermit
      		Inj. setup to 45MeV 	Inj setup to 45 MeV
      			Inj parity checks(Yves?)
      2009-08-10 Mon 	ops 24/7 	NL:Restricted Access 	CEBAF:PowerPermit
      			Emax:2L17,2L18,1L05,1L10
      		Inj Parity checks 	Inj parity checks
      		up to 500keV(Yves?/HappexIII) 	up to 45 MeV(Yves?)
      			
      2009-08-11 Tue 	Power Permit:CEBAF 	NL: Restrct Acc.
      Emax:2L17,2L18,1L05,1L10
      RECO:Lauze 		SL: PP 	
      		C50-9 4k pumpdown 	
      			
      2009-08-12 Wed 	CEBAF:PowerPermit 	NL Restricted Access
      CEBAF:PowerPermit
      PD:YanWang 		SL Power Permit 	
      		C50-9 2K pumpdown 	
      		Heat/Reactivate Cathode? 	parasiticQ:1L05,1L10,2L17,2L18
      2009-08-13 Thu 	CEBAF:PowerPermit 	CEBAF:PowerPermit
      CEBAF:PowerPermit
      			
      	parasiticQ:1L05,1L10,2L17,2L18 	Inj to 45 MeV 	Inj to 45 MeV
      		Parity Quality (Yves) 	Parity Quality(Yves)
      		MO swing? (Tief) 	MO swing?(Tief)
      			parasiticQ:1L05,1L10,2L17,2L18
      2009-08-14 Fri 	CEBAF:PowerPermit 	CEBAF:PowerPermit
      CEBAF:PowerPermit
      			
      	All systems ON 	Start beam recovery 	5.9 GeV balanced setup
      	parasiticQ:1L05,1L10,2L17,2L18 	5.9 GeV balanced setup 	
      		MO swing?(Tief) 	
      2009-08-15 Sat 	CEBAF:PowerPermit 	CEBAF:PowerPermit 	
      	5.9GeV bal. setup 	5.9GeV bal. setup 	....
      			
      2009-08-16 Sun 			
      	.... 	.... 	....
      			
      2009-08-17 Mon 		CEBAF:open if needed 	5.76 GeV unbal. setup
      	... 	for repairs 	
      		5.76 GeV unbal. setup 	
      2009-08-18 Tue 	5.76GeV unbal. setup 	5.76GeV unbal. setup
      5.76GeV unbal. Beam
      		1/5/2 pass separation 	1/5/2 separation
      		BSY Beam matching 	BSY Beam matching
      			
      2009-08-19 Wed 	5.76GeV unbal. Beam 	Beam to Halls 	Beam to Halls
      PD: Kazimi 	CW to BSY dump 	BSY Beam matching 	Energy Spread opt.
      			Parity quality checks
      			
      2009-08-20 Thu 	Beam to Halls 	Beam to Halls 	Beam to Halls
      	Energy Spread opt. 	Energy Spread opt. 	Energy Spread opt.
      			
      2009-08-21 Fri 	Beam to Halls 	Physics 	Physics
      			
      			

Date: 2009-08-11 14:49:11 EDT

HTML generated by org-mode 6.28e in emacs 22


-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/bteam/attachments/20090811/c0a2b27f/attachment-0002.html>


More information about the BTeam mailing list