Proposed start up sequence in January. I'd like to get some time to
work on the pathlength monitors, mo-mod and pre-buncher during the startup.
Will the Halls be ready by Thursday? Discuss at Wednesday's
B-team? Happy Trails and Holidays!
Arne
January 2011 startup strawman
2010-12-17 Fri
1 Monday January 3rd
OWL Shift
lock up the machine (INJ, NL, SL, BSY) turn on as much as possible.
Make a list for Day shift to work through, no call ins. Radcon check
lists?
DAY Shift
Continue the process of getting the machine locked up. Gun on and
beam to 500keV if possible.
SWING Shift
Restore beam to 2010-12-23 Thu settings, five pass
2 Tuesday January 4th
OWL Shift
Continue 5-pass restoration, start ORFP
DAY Shift
Continue ORFP, pathlength monitor checks
SWING Shift
Download new ARC1, ARC2...(ARCn) optics. Repeat ORFP
3 Wednesday January 5th
OWL Shift
Finalize 5-pass setup, CW to BSY dump
DAY Shift
Beam Studies, pre-buncher, high current injector setup
SWING Shift
QWeak Injector studies
4 Thursday January 6th
OWL Shift
1-pass separation, 5-pass magnetic? (or RF?) separation
DAY Shift
Beam Studies
Swing Shift
Resume beam for Physics.
Date: 2010-12-17 13:30:14 EST
HTML generated by org-mode 6.33x in emacs 23
--
Director of Accelerator Operations
Jefferson Lab Office: (757) 269-6268
12000 Jefferson Avenue Cell: (757) 876-6289
Newport News, VA 23606 Email: freyberg at jlab.org
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/bteam/attachments/20101217/3a52ac4b/attachment-0002.html>
More information about the BTeam
mailing list