[Bteam] B-Team prioritized tests for Thurs-Fri beam studies
wrainey at jlab.org
wrainey at jlab.org
Thu Jul 22 08:33:07 EDT 2010
Team,
Hall B is expected to require beam until at least 1700 today so I will
have to slide the schedule below a bit. This may impact our ability to
complete the last test on the list below.
Bill
> Bill, et al.,
>
> The list of studies proposed at the bteam meeting included these, listed
> in order of recommended execution with shifts indicated.
>
> Thursday swing shift:
> 15:00-17:00
> Injector RF measurements (Inj only) -- Kazimi 2 hr
>
> 17:00-22:00
> RF calibration protocol development (beam to 1R) -- Tiefenback 5 hr
>
> 22:00-23:00 spilling over to owl shift 23:00-06:00
> Helicity corr. asymmetry (Inj ; 8 hr total) -- Paschke/Dalton 1 hr
> Friday owl shift:
> Helicity corr. asymmetry (Inj ; ) -- Paschke/Dalton 7 hr
>
> 06:00-07:00 spilling over to day shift 07:00-08:00
> Injector model comparisons (Inj only) -- Law/Hofler 1 hr
> Friday day shift:
> Injector model comparisons (Inj only) -- Law/Hofler 1 hr
>
> 08:00-10:00
> Gun Transmission with variable laser pulse (Inj) -- Tiefen 2 hr
>
> 10:00-12:00
> Chopper differential T.o.F./energy on A/B/C path -- Tiefen/Kazimi 2 hr
>
> Then revert to Hall B's 2-pass setup for their prospective physics run.
>
> Comments and improvements are welcome from all ... don't be shy.
> The Chopper differential T.o.F./energy ATLis remains to be written,
> although I have discussed it with Reza periodically for years.
>
> Michael Tiefenback
>