Jay - Thursday is fine for me, although if time avails Reza & I would
like the ~couple hours as planned for Tuesday BS.
Jay Benesch wrote:
> Steve called to ask what I see for test plans because he needs to get
> the last refurbished CM into the SL before the August power outage in
> the Test Lab take out their cranes.
>
> I replied:
>
> 5.6 GeV cleanup tomorrow
> Spata optics measurements in arc 1 Thursday?
> A1 corrector hook-up and checkout Thursday?
> Two JT valve flow tests in the SL Tuesdays July 6 and 13?
> Paschke helicity correlated beam properties test
>
> Looking at ATLis after the phone call, I also see:
>
> active collimator lock test - whenever B agrees
> Qweak optics work for adiabatic damping as necessary
> spin flipper performance test
>
>
> Steve will decide when to take the six hours in the SL to install the CM.
>
> Jay
>