[Bteam] test plan meeting minutes

Jay Benesch benesch at jlab.org
Tue Nov 23 09:45:04 EST 2010


The meeting was irresolute.

Spin dance planned for today may have to be deferred due to Moller 
solenoid cryostat problems in hall C.  TBD by 1000.

Hall B will come back on line some time Tuesday 11/30.

The only test plan definitely scheduled for 11/30 is
http://opsweb.acc.jlab.org/CSUEApps/atlis/task/10511
This uses fopt in arc 9 to take data for model calibration.  Fifth pass 
beam will have to be established to the B dumplet for the test.  I 
suggest pathlength be adjusted before the test too.

If Hall B is ready to lock up by 1000 Ops will likely move into that 
setup immediately.  If Hall B isn't ready until swing shift there will 
be physics delivery for A and C.  This beam delivery might be the spin 
dance if hall C Moller has been fixed.

In other words, things are fluid and will remain so.