[Bteam] Thursday is going to be a very full day. Friday won't be much better

Jay Benesch benesch at jlab.org
Tue Apr 17 15:19:43 EDT 2012


Feel free to forward this.

0700	RadCon survey of SL and then BSY

0730	SRF entry into SL for piezo work, estimate 6 hours to complete
		http://opsweb.acc.jlab.org/CSUEApps/atlis/task/12322
		is the only ATLis I can find

0700	injector work in parallel, likely a two hour PEPPO test

0745	halls can request of PD controlled or restricted access

0900? 	gun HV off, short injector entry, QE scan, etc.  total ~1h

0900-1200  ten ARMs will be in refresher course in RadCon trailer

1000-1600  additional PEPPO tests

1300	begin RF recovery of two zones in NL turned off last week

1330	lock up SL and BSY

1400	C100 work begins from upstairs

1415-1630  BIW tours.  Four busloads visiting MCC, FEL, Hall D, ?
	Arne, Mike T., Todd S. and Jay talking at MCC.

1430	begin RF recovery of six SL zones turned off last week

1600	bring up magnets and as much RF as possible
	DC power support needed as something will have broken due to
		on/off/on cycle
	Use BURT and MST to get correct BdLs into magnets
	
1630	spot move, Wien flip and HWien set ~1.5 hours

1800	high current setup at 61.6 MeV

2000	C100 work ends.  Restore 548/linac begins in earnest.
	http://opsweb.acc.jlab.org/CSUEApps/atlis/task/12320

~2200	first pass beam around with all cavities phased

~2359	ready to RF separate first pass to A, third to C. Fifth to B

Friday

0400??	low current beam to A, B, C.  C will take under 3uA to ~1300.

1300-1700  high current setup to C including C100 tuning as required

1300-1600  ten ARMs in refresher course in RadCon trailer

1300-1500 Qweak physics meeting



More information about the BTeam mailing list