I would like to clean up the Beam Test Plan area so that it only holds
test plans that are likely to be executed between now and May 18th.
Any test plan that doesn't apply beyond 6GeV operations should be
deleted. Test plans for hot check out should be deleted as the whole
hot check out process will be new for 12GeV (I've already deleted the
AHLA hot checkout items).
Either delete/complete the test plans you own or place a comment on why
you think they should remain on the list by COB today. Tonight/Tomorrow
I'll clean things out.
Arne
--