[Bteam] Beam Studies for today

Arne Freyberger freyberg at jlab.org
Wed Mar 21 09:35:59 EDT 2012


Even this updated list is out of date.   But in broad strokes:

  * 8:30-9:00 all saves
  * 9:00-5:00 C100 work without beam
  * In parallel:
      o PEPPo work 9:00-1:30, Joe has re-prioritized his plans see him
        for the details
      o 1:30'ish Injector Steering test
      o 3:30'ish M_56 measurements
  * 5:00 pm beam in the machine
  * 5:00-7:00pm LOCO measurements in an Arc that makes Yves Happy.
  * 7:00-9:00pm recovery

LOCO measurement may take less time.    If C100 finish early, the M_56 
and the Injector Steering test may get cut.

Arne


      2.1 This Week \\ 2012-03-21 Wednesday

All beam studies tasks this week will be opportunistic.


Scheduled Tasks 	Expected 	Actual 	Campaign 	Beam

	Duration 	
	
	Termination

	(h) 	
	
	
Initial fOpts/Allsaves 	0.5 	
	Program 	B & C
C100 Test Cont. <http://opsweb.acc.jlab.org/CSUEApps/atlis/task/12198> 	8 	
	C100 	Inj.
PEPPo Electron Beam Transport 
<http://opsweb.acc.jlab.org/CSUEApps/atlis/task/11885> 	2 	
	PEPPo 	Inj.
PEPPo BCM0L02 A_Q @ 100nA 
<http://opsweb.acc.jlab.org/CSUEApps/atlis/task/12199> 	1.5 	
	PEPPo 	Inj
PEPPo Fiber Array Commissioning 
<http://opsweb.acc.jlab.org/CSUEApps/atlis/task/12201> 	1 	
	PEPPo 	Inj
Injector Steering Test 
<http://opsweb.acc.jlab.org/CSUEApps/atlis/task/12017> 	2 	
	Misc. 	Inj
Measure M_56 Inj. Chicane 
<http://opsweb.acc.jlab.org/CSUEApps/atlis/task/12124> 	1 	
	Model 	Inj
Arc4 Model Calibration 
<http://opsweb.acc.jlab.org/CSUEApps/atlis/task/12094> 	2 	
	Model 	4R or 5R
Restoration 	2.0 	
	Program 	B&C
Parasitic Hours 	-7.5 	
	
	
Total 	12.5 	
	
	

2 This Week \\ 2012-03-21


    3 Next Week \\ 2012-03-21 Wed


      3.1 Preliminary Beam Studies Program \\ Next Week: 2012-03-14 Wed

Beam Studies will be finalize at Friday 9am MCC Beam Studies Scheduling 
meeting.
.
.
C100: 2L24 gradient push!!! Onward, upward to 98MeV!!!!
Modeling! PEPPo! Mott!

Date: $\today$

Author: Arne Freyberger

Org version 7.5 with Emacs version 23

Validate XHTML 1.0 <http://validator.w3.org/check?uri=referer>

-- 
Arne Freyberger
Director of Accelerator Operations
Jefferson Lab           Office: (757) 269-6268
12000 Jefferson Avenue  Cell:   (757) 876-6289
Newport News, VA 23606  Email:  freyberg at jlab.org

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/bteam/attachments/20120321/29d3b92a/attachment-0002.html>


More information about the BTeam mailing list