Dear BTeamers,
We are nearing the end of the Hall B low energy run, with a significant
period yesterday concentrated on tuning up the machine for second pass
beam delivery to PRad. That effort was close to converging overnight,
but ran out of time before the nominal Hall B opening. This afternoon,
after isotope activities in the injector, we plan to get 2C04 quad
scan data for input optics conditions to the 2C line (but not load
a match), then finish up tightening the beam spot with the 2C triplet
for PRad operations.
The next few days have potential PQB tests and/or NL access combined
with SL RF tests tomorrow (Weds Jun 15) and injector tests (Thu Jun 16).
We also hope to hear some input on a possible PRad extension of order
of a few days later today.
Given the fairly clear path ahead and the proximity of the end of the
run, there is no BTeam meeting today.