[BTeam] Bteam today.
Yves Roblin
roblin at jlab.org
Tue Apr 7 08:52:00 EDT 2020
We will have a bteam today. I would like to start fleshing out the strategy to restart the machine so that we can get started developing a gant like last time.
Amongst things to ponder :
1) Restart as is, just check optics in injector and transverse optics in machine.
2) same as 1) but take time to characterize alternate arc1 optics
3) like 2) but decide to leave the new arc1 optics and rematch accordingly
Things we know we have to do :
Transtition 4k to 2k
Assess/recover RF
Assess/tune injector
Check high current setup/loss in east arc ( maybe go to bsy dump at pass 3, loss is enough to be seen at lower current) .
Recheck incoming arc opticdls
Validate beam parity quality
Let's come to the meeting and make a list.
Sent from my Verizon, Samsung Galaxy smartphone
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/bteam/attachments/20200407/ba02d019/attachment.html>
More information about the BTeam
mailing list