[BTeam] Tuesday March 17 B team

Todd Satogata satogata at jlab.org
Mon Mar 16 12:07:34 EDT 2020


Hi folks,

Crystal will be setting up a BlueJeans connection for this meeting
tomorrow; we will distribute through the bteam mailing list.

                                                 -Todd

======================================================================
Todd Satogata
Director, Center for Advanced Studies of Accelerators
Jefferson Lab
12000 Jefferson Avenue
Newport News, VA 23606
Cell: (631) 807-0674
======================================================================

On 3/16/20 9:47 AM, Jay Benesch wrote:
> Colleagues,
> 
> Camille would like to discuss issues associated with the Hall C laser.
> 
> 1. Results of the test BLM vs C slit width at constant current (Tiefenback or Roblin)
> 
> 2. Implications of the stability of A2 interception since C turned off Friday https://logbooks.jlab.org/entry/3804851
> 
> Other items
> 
> 3. Is heat/activation needed before the end of the run? See elog above. If so, this week given B and C both down?
> 
> 4. Could the UITF seed laser be swapped for the C seed laser?  Less work downstairs than swapping B and C and it provides CIS with a way to investigate what's wrong with C seed offline.
> 
> 5. Is it appropriate to revert to the 4 m dispersion optics in Hall C for d2n? http://opsweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=20434
> 
> 6. TBD
> 
> Jay
> _______________________________________________
> BTeam mailing list
> BTeam at jlab.org
> https://mailman.jlab.org/mailman/listinfo/bteam





More information about the BTeam mailing list