[BTeam] Upcoming Beam Study Opportunities (Please Sign Up)

Dennis Turner dturner at jlab.org
Tue Aug 10 14:23:54 EDT 2021


Hi Mike,

  I signed up to do MultiWire and rayTrace testing on August 16 Day shift.

Dennis

________________________________
From: BTeam <bteam-bounces at jlab.org> on behalf of Michael Aiken <aiken at jlab.org>
Sent: Monday, August 9, 2021 2:41 PM
To: bteam at jlab.org <bteam at jlab.org>; John Musson <musson at jlab.org>; Adam Carpenter <adamc at jlab.org>; Christopher Slominski <cjs at jlab.org>; Matthew Poelker <poelker at jlab.org>; Joe Grames <grames at jlab.org>; Marcy Stutzman <marcy at jlab.org>; Clyde Mounts <mounts at jlab.org>; Ramakrishna Bachimanchi <bachiman at jlab.org>; Tomasz Plawski <plawski at jlab.org>
Cc: Christiana Wilson <grenoble at jlab.org>
Subject: [BTeam] Upcoming Beam Study Opportunities (Please Sign Up)

Hello Gentle Folk!
We currently have beam to 2R with intentions of beam to 3R at the end of today.  Beam tuning progress will get halted periodically as we wait for downstream box supply repairs.

I've populated a calendar with what I know, and where we will prospectively have time for beam studies.  I do not know what everyone's schedules are, but I've highlighted (in yellow) the times that are projected to be available for beam studies.  Please take a look, and sign up for a shift ("daily activities" tab):

[https://outlook-1.cdn.office.net/assets/mail/file-icon/png/xlsx_16x16.png]2021Restore.xlsx<https://jeffersonlab-my.sharepoint.com/:x:/g/personal/aiken_jlab_org/EXRNlMFRk31FsO7i0RrrZSIBD_6pG-6WZalra3ljScyHlw?e=ub8yCI>

Here's a list of items that come to mind:

  *   Multi wire emmitance - 4h - Turner - https://opsweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=19784
  *   Ray Trace - 2h - Turner - https://opsweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=21000
  *   MoMod - 4h - Tiefenback/Musson (No Atlis)
  *   2A SLM Commissioning - 2h - Freeman
  *   Setting Bunch Compression - 4h - Freeman - https://opsweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=19811
  *   RF Field Emission Testing Data - 4h - Carpenter - https://opsweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22602
  *   Gradient Cal - 4h - Slominski/Carpenter - https://opsweb.acc.jlab.org/CSUEApps/atlis/atlis.php?load=Task&task_id=22480
  *   Finalizing 1L05 Settings- Plawski/Bachimanchi/Mounts
  *   Ion Gap Clearing Test - 2h - Grames/Poelker - https://opsweb.acc.jlab.org/CSUEApps/atlis/task/19804
  *   Mott Measurements - 8h - Grames/Stutzman
  *   1S / 2S Common Dipole Steering (?No Atlis?) - 4h
  *   Test Steering Effects of the West Arc Dipoles on 0R region (No Atlis) - 2h
  *   Minimize Field Emmission from C100s (No Atlis) - 4h

If you have other ideas, please let myself and the PD know.
The spreadsheet is still being developed and will be continuously evolving as we progress.

-Mike Aiken


-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/bteam/attachments/20210810/ebe2c0cb/attachment.html>


More information about the BTeam mailing list