Here it is with the approximate starting/ending times adjusted after feedback from  testplan writers on more accurate estimates. Still, if you are scheduled to do a testplan that day, please be available in case the previous testplan ends up earlier.

Start
Duration
Description
Lead
Task link
Comment
7:00
1:00
Save machine setup
Crew Chief
https://tasklists.jlab.org/bslist/tasks/110441
8:00
4:00
FFB
D. Turner, R. Bodenstein
https://tasklists.jlab.org/bslist/tasks/110062
Last to require Hall C
12:00
1:30
Momentum acceptance of injector chicane
D. Turner
https://tasklists.jlab.org/bslist/tasks/110432
13:30
1:30
Cavity Field Emission Measurement
A. Carpenter
https://tasklists.jlab.org/bslist/tasks/24352
15:00
2:00
BLM sensitivity to energy offset
J. Benech, K. Price
https://tasklists.jlab.org/bslist/tasks/108265
17:00
6:00
BLM sensitivity via Apperture Scan
J. Benesch, K. Price
https://tasklists.jlab.org/bslist/tasks/110398
23:00
6:00
Operator training
D. Moser, B. Freeman
5:00
8:00
K-Long Beam Studies at 180 kV
S. Pokharel
https://tasklists.jlab.org/bslist/tasks/110315
13:00
4:00
Photocathode effects from KLong beam
R. Suleiman
https://tasklists.jlab.org/bslist/tasks/110188
17:00
Adjourn

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/bteam/attachments/20231213/9416bf34/attachment-0001.html>


More information about the BTeam mailing list