[BTeam] beam studies for today

Yves Roblin roblin at jlab.org
Wed Feb 28 08:52:13 EST 2024


Start
Duration
Description
Lead
Task link
7:00
3:00
Access to injector and maintenance
Maintenance

10:00
3:00
New helicity generator board test
Riad
FC2? Not compatible with NL access
13:00
2:00
Injector beam size measurement and injector check check
Yan

15:00
1:00
NL calibration
Jay
CEBAF RF ready by 3 pm
16:00
1:00
Restore beam to Hall C
Operators
Hall C ready at 4 pm
17:00
2:00
Bunch length measurements
Brian

19:00
2:00
Beam restore/CEBAF tuning/contingency
Operators

21:00

Beam to physics




If the helicity board test cant be done to FC1, we can swap Yan and Riad order of execution. Talking to techs this morning, they expect to have the NL locked around noon.


-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/bteam/attachments/20240228/6456d6e9/attachment.html>


More information about the BTeam mailing list