1. BLM cal 8AM-10AM, HALLA has access. ATLIS 107920
2. FFB in Hall A, 25uA CW and up . 3 hours , 10AM to 1 PM
3. Raytrace 1PM -130PM ATLIS 111826
4. Injector tune for KLONG 130PM -530PM, SRF cavity emission test in //,DAQ cal testplan
increase HV on two of the RF zones in SL.
5. BLA cal, high current push 530PM ->1030pm
6. KLONG testing 1030pm ->5am ( HALLC KLONG and HALLA 40 uamps CW)
7. QTSnyder 5am->7am optional.
The decision to run step 6, KLONG testing will be made after the injector retune if we get a successful setup with this injector configration (140 KV, bad solenoids).