[BTeam] proposal for end of Wednesday owl
Jay Benesch
benesch at jlab.org
Sun Apr 20 19:38:11 EDT 2025
Wednesday is a maintenance day. I propose that one hour before we plan
to take beam away from BCD we ask C to pull their target and turn off
all the detector voltages. Then we put as much current as we can into
the C dump. This will may identify RF and optics issues which have to
be addressed before A switches to fifth pass. RF maintenance priorities
could be adjusted. Optics work plans could be developed.