    The plan for this upcoming Wednesday is(assuming a 8am start time):<br>
    <ol>
      <li>FOpt to Hall-B and Hall-C, all saves  and other associated
        start of beam studies tasks</li>
      <ol>
        <li>30minutes<br>
        </li>
        <li><b>Need beam to Hall B &C</b><br>
        </li>
      </ol>
      <li>New current lock checkout (Hofler) </li>
      <ol>
        <li>30minutes of actual beam time </li>
        <li><a class="moz-txt-link-freetext" href="http://opsweb.acc.jlab.org/CSUEApps/atlis/task/11850,http://opsweb.acc.jlab.org/CSUEApps/atlis/task/11851">http://opsweb.acc.jlab.org/CSUEApps/atlis/task/11850,http://opsweb.acc.jlab.org/CSUEApps/atlis/task/11851</a></li>
        <li><b>Need beam to the Hall B & C</b></li>
      </ol>
      <li>Peppo tests (Grames)<br>
      </li>
      <ol>
        <li>6hours of beam time (max, will probably be less)<br>
        </li>
        <li><a class="moz-txt-link-freetext" href="http://opsweb.acc.jlab.org/CSUEApps/atlis/task/11532">http://opsweb.acc.jlab.org/CSUEApps/atlis/task/11532</a>,
          <a class="moz-txt-link-freetext" href="http://opsweb.acc.jlab.org/CSUEApps/atlis/task/11780">http://opsweb.acc.jlab.org/CSUEApps/atlis/task/11780</a></li>
        <li><b>Beam to 5MeV section (Inj/NL must remain locked up)</b><br>
        </li>
      </ol>
      <li>Mott test (Riad)<br>
      </li>
      <ol>
        <li>2 hours of the requested 4hours<br>
        </li>
        <li><a class="moz-txt-link-freetext" href="http://opsweb.acc.jlab.org/CSUEApps/atlis/task/11849">http://opsweb.acc.jlab.org/CSUEApps/atlis/task/11849</a></li>
        <li><b>Beam to 5MeV section (Inj/NL must remain locked up)</b><br>
        </li>
      </ol>
      <li>Modeling tests (Todd)<br>
      </li>
      <ol>
        <li>Only if time permits, needs about 1.5hours<br>
        </li>
        <li><a class="moz-txt-link-freetext" href="http://opsweb.acc.jlab.org/CSUEApps/atlis/task/9741">http://opsweb.acc.jlab.org/CSUEApps/atlis/task/9741</a></li>
        <li><b>Need beam permit in all sections, up to and including BSY</b><br>
        </li>
      </ol>
    </ol>
    <p>Note that the rough plan is schedule about 8hours of beam studies
      to allow sufficient time for recovery and the resumption of
      physics promptly at 8pm.   In that sense beam studies proper
      should be terminated around 5pm to allow for 3hours of beam
      restorations.  Hall should be ready for beam (locked up, in beam
      permit) 5pm'ish, 6pm at the latest. <br>
    </p>
    <p>For Wednesday Jan 11th, the beam studies (PEPPo, Mott) are in the
      injector.  Maintenance or other efforts in parallel with these
      beam studies (mostly confined to SL) needs to closely
      coordinated/approved with optics-on-call as they will need to pick
      up the pieces of any hardware changes.<br>
    </p>
    <p>Arne<br>
    </p>
    <pre class="moz-signature" cols="72">-- 
Arne Freyberger
Director of Accelerator Operations
Jefferson Lab           Office: (757) 269-6268  
12000 Jefferson Avenue  Cell:   (757) 876-6289  
Newport News, VA 23606  Email:  <a class="moz-txt-link-abbreviated" href="mailto:freyberg@jlab.org">freyberg@jlab.org</a>
</pre>
  </body>
</html>