The plan for this upcoming Wednesday is(assuming a 8am start time):<br>
<ol>
<li>FOpt to Hall-B and Hall-C, all saves and other associated
start of beam studies tasks</li>
<ol>
<li>30minutes<br>
</li>
<li><b>Need beam to Hall B &C</b><br>
</li>
</ol>
<li>New current lock checkout (Hofler) </li>
<ol>
<li>30minutes of actual beam time </li>
<li><a class="moz-txt-link-freetext" href="http://opsweb.acc.jlab.org/CSUEApps/atlis/task/11850,http://opsweb.acc.jlab.org/CSUEApps/atlis/task/11851">http://opsweb.acc.jlab.org/CSUEApps/atlis/task/11850,http://opsweb.acc.jlab.org/CSUEApps/atlis/task/11851</a></li>
<li><b>Need beam to the Hall B & C</b></li>
</ol>
<li>Peppo tests (Grames)<br>
</li>
<ol>
<li>6hours of beam time (max, will probably be less)<br>
</li>
<li><a class="moz-txt-link-freetext" href="http://opsweb.acc.jlab.org/CSUEApps/atlis/task/11532">http://opsweb.acc.jlab.org/CSUEApps/atlis/task/11532</a>,
<a class="moz-txt-link-freetext" href="http://opsweb.acc.jlab.org/CSUEApps/atlis/task/11780">http://opsweb.acc.jlab.org/CSUEApps/atlis/task/11780</a></li>
<li><b>Beam to 5MeV section (Inj/NL must remain locked up)</b><br>
</li>
</ol>
<li>Mott test (Riad)<br>
</li>
<ol>
<li>2 hours of the requested 4hours<br>
</li>
<li><a class="moz-txt-link-freetext" href="http://opsweb.acc.jlab.org/CSUEApps/atlis/task/11849">http://opsweb.acc.jlab.org/CSUEApps/atlis/task/11849</a></li>
<li><b>Beam to 5MeV section (Inj/NL must remain locked up)</b><br>
</li>
</ol>
<li>Modeling tests (Todd)<br>
</li>
<ol>
<li>Only if time permits, needs about 1.5hours<br>
</li>
<li><a class="moz-txt-link-freetext" href="http://opsweb.acc.jlab.org/CSUEApps/atlis/task/9741">http://opsweb.acc.jlab.org/CSUEApps/atlis/task/9741</a></li>
<li><b>Need beam permit in all sections, up to and including BSY</b><br>
</li>
</ol>
</ol>
<p>Note that the rough plan is schedule about 8hours of beam studies
to allow sufficient time for recovery and the resumption of
physics promptly at 8pm. In that sense beam studies proper
should be terminated around 5pm to allow for 3hours of beam
restorations. Hall should be ready for beam (locked up, in beam
permit) 5pm'ish, 6pm at the latest. <br>
</p>
<p>For Wednesday Jan 11th, the beam studies (PEPPo, Mott) are in the
injector. Maintenance or other efforts in parallel with these
beam studies (mostly confined to SL) needs to closely
coordinated/approved with optics-on-call as they will need to pick
up the pieces of any hardware changes.<br>
</p>
<p>Arne<br>
</p>
<pre class="moz-signature" cols="72">--
Arne Freyberger
Director of Accelerator Operations
Jefferson Lab Office: (757) 269-6268
12000 Jefferson Avenue Cell: (757) 876-6289
Newport News, VA 23606 Email: <a class="moz-txt-link-abbreviated" href="mailto:freyberg@jlab.org">freyberg@jlab.org</a>
</pre>
</body>
</html>