    Colleagues,<br>
        In order to maintain momentum at this critical time in the
    commissioning, the concept of a supplemental LASO is being
    re-instated with the tentative schedule below.   A twist in the
    Supplement-LASO is that the SLASO shifts are offset by 4h from the
    nominal shifts.  This is done to provide seem-less continuity during
    this intense period.  The schedule has not been completely filled
    out and if you wish to volunteer for a SLASO shift, please let me
    know.     As some of you who have been assigned a SLASO shift are
    hearing about it the first time, I expect there will be some horse
    trading.   In addition to the schedule below,  there is a chart of
    the progress since the ZA affair.  Progress is on schedule, but due
    to the recent down times (CHL1 trips, dumplet issues)  there is no
    room left for inefficient operation.<br>
    <br>
    Arne and Mike<br>
    <pre>1 Supplemental LASO                                                :OPS:
===================

  --------------------------------------------------------------------------------------------------------------------------------------------------
   Day Name   Date           Owl         Owl-Sup        Day       Day-Sup         Swing       Swing-Sup     Comment                                 
                                         4am-noon                 noon-8pm                    8pm-4am                                               
                                         (Duck Hunter)            (Country Club)              (Night Club)                                          
  --------------------------------------------------------------------------------------------------------------------------------------------------
   Friday     May-02         Morozov                    Terzic                    Wang                      Beam tuned to                           
                                                                                              Spata         4/5R, CHL-1 trip                        
  --------------------------------------------------------------------------------------------------------------------------------------------------
   Saturday   May-03         Morozov                    Benesch                   Grames                    Beam to 5C dumplet,finish 550MeV/linac  
                                         Freyberger                                           Tiefenback    start scaling to 910MeV/linac           
  --------------------------------------------------------------------------------------------------------------------------------------------------
   Sunday     May-04         Suleiman                   Roblin                    Freyberger                910MeV/linac ORFP                       
                                                                                                                                                  
  --------------------------------------------------------------------------------------------------------------------------------------------------
   Monday     Cinco de Mayo  Benson                     Ahmad                     Tiefenback                document 10GeV to 5C                    
                                         Satogata                                                           Day shift: PSS certs/authorization      
                                                                                                            Swing shift: plow beam into tagger dump 
  --------------------------------------------------------------------------------------------------------------------------------------------------
   Tuesday    May-06         Krafft                     Benesch                   Douglas                   Restore 550MeV/linac, start             
                                         Freyberger                                                         Optics program                          
  --------------------------------------------------------------------------------------------------------------------------------------------------
   Wednesday  May-07         Grames                     Stutzman                  Bogacz                                                            
                                                                                                                                                  
  --------------------------------------------------------------------------------------------------------------------------------------------------
   Thursday   May-08         Krafft                     Kazimi                    Satogata                                                          
                                                                                                                                                  
  --------------------------------------------------------------------------------------------------------------------------------------------------
   Friday     May-09         Tiefenback                 Wang                      Zhang                                                             
                                                                                                                                                  
  --------------------------------------------------------------------------------------------------------------------------------------------------
</pre>
    <img src="cid:part1.00010206.06050509@jlab.org" alt="">
    <pre class="moz-signature" cols="72">-- 
Arne Freyberger
Director of Accelerator Operations
Jefferson Lab             
12000 Jefferson Avenue      Cell: (757) 876-6289
Postal Suite 19             Email:  <a class="moz-txt-link-abbreviated" href="mailto:freyberg@jlab.org">freyberg@jlab.org</a> 