Colleagues,<br>
In order to maintain momentum at this critical time in the
commissioning, the concept of a supplemental LASO is being
re-instated with the tentative schedule below. A twist in the
Supplement-LASO is that the SLASO shifts are offset by 4h from the
nominal shifts. This is done to provide seem-less continuity during
this intense period. The schedule has not been completely filled
out and if you wish to volunteer for a SLASO shift, please let me
know. As some of you who have been assigned a SLASO shift are
hearing about it the first time, I expect there will be some horse
trading. In addition to the schedule below, there is a chart of
the progress since the ZA affair. Progress is on schedule, but due
to the recent down times (CHL1 trips, dumplet issues) there is no
room left for inefficient operation.<br>
<br>
Arne and Mike<br>
<pre>1 Supplemental LASO :OPS:
===================
--------------------------------------------------------------------------------------------------------------------------------------------------
Day Name Date Owl Owl-Sup Day Day-Sup Swing Swing-Sup Comment
4am-noon noon-8pm 8pm-4am
(Duck Hunter) (Country Club) (Night Club)
--------------------------------------------------------------------------------------------------------------------------------------------------
Friday May-02 Morozov Terzic Wang Beam tuned to
Spata 4/5R, CHL-1 trip
--------------------------------------------------------------------------------------------------------------------------------------------------
Saturday May-03 Morozov Benesch Grames Beam to 5C dumplet,finish 550MeV/linac
Freyberger Tiefenback start scaling to 910MeV/linac
--------------------------------------------------------------------------------------------------------------------------------------------------
Sunday May-04 Suleiman Roblin Freyberger 910MeV/linac ORFP
--------------------------------------------------------------------------------------------------------------------------------------------------
Monday Cinco de Mayo Benson Ahmad Tiefenback document 10GeV to 5C
Satogata Day shift: PSS certs/authorization
Swing shift: plow beam into tagger dump
--------------------------------------------------------------------------------------------------------------------------------------------------
Tuesday May-06 Krafft Benesch Douglas Restore 550MeV/linac, start
Freyberger Optics program
--------------------------------------------------------------------------------------------------------------------------------------------------
Wednesday May-07 Grames Stutzman Bogacz
--------------------------------------------------------------------------------------------------------------------------------------------------
Thursday May-08 Krafft Kazimi Satogata
--------------------------------------------------------------------------------------------------------------------------------------------------
Friday May-09 Tiefenback Wang Zhang
--------------------------------------------------------------------------------------------------------------------------------------------------
</pre>
<img src="cid:part1.00010206.06050509@jlab.org" alt="">
<pre class="moz-signature" cols="72">--
Arne Freyberger
Director of Accelerator Operations