    <pre>                   ━━━━━━━━━━━━━━━━━━━━
                           REMAINING SCHEDULE


                            Arne Freyberger
                          ━━━━━━━━━━━━━━━━━━━━


1 Supplemental LASO                                                :OPS:
═══════════════════

1.1 Update 1:
─────────────

  Significant progress over the weekend.  5.5pass CEBAF is a reality.
  Scaling to 950MeV/linac started on Saturday.  Some self-immolation on
  Saturday, scaling the corners not the best thing to do.  By Sunday
  afternoon, ORFP of the 950MeV/linac was proceeding smoothly.  Beam to
  6R, ORFP complete to 5R.  Then the wall, multiple hardware issues took
  CEBAF offline for about 12h.


  Today, at present, the Hall-D PSS certifications are underway.  It is
  hoped that the ORFP of the 950MeV/linac configuration can get back on
  track on Swing/Owl tonight.

  Notable items:
  ⁃ start with the "corners" on design and tweak from there.  If corners
    are not on design when beam first traverses an arc, put them there.
  ⁃ Use CMPQ to verify dipoles are at or near design
  ⁃ Pathlength, dispersion, courant snyder


1.2 Schedule
────────────

  ━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
   Day Name   Date           Owl         Owl-Sup        Day       Day-Sup         Swing       Swing-Sup     Comment                            
                                         4am-noon                 noon-8pm                    8pm-4am                                          
                                         (Duck Hunter)            (Country Club)              (Night Club)                                     
  ─────────────────────────────────────────────────────────────────────────────────────────────────────────────────────────────────────────────
   Monday     Cinco de Mayo  Benson                     Ahmad                     Tiefenback                Owl: Downhard                      
                                         Benesch                                                            Day shift: PSS certs/authorization 
                                                                                                            Swing shift: 10GeV to 5C!!         
  ─────────────────────────────────────────────────────────────────────────────────────────────────────────────────────────────────────────────
   Tuesday    May-06         Krafft                     Benesch                   Douglas                   Owl: 10GeV to 5C                   
                                         Freyberger                                           Satogata      Day/Swing: 10GeV to Tagger dump?   
  ─────────────────────────────────────────────────────────────────────────────────────────────────────────────────────────────────────────────
   Wednesday  May-07         Tiefenback                 Stutzman                  Bogacz                    Restore 550? or Optics at 950?     
                                         Freyberger               Roblin                      Satogata                                         
                                         (if needed)                                                                                           
  ─────────────────────────────────────────────────────────────────────────────────────────────────────────────────────────────────────────────
   Thursday   May-08         Krafft                     Kazimi                    Satogata                  Opics                              
                                                                  Roblin                                                                       
  ─────────────────────────────────────────────────────────────────────────────────────────────────────────────────────────────────────────────
   Friday     May-09         Grames                     Wang                                                INJ/NL locked up until noon        
                                         Hofler                                                                                                
                                                                                                                                             
  ━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

</pre>
    <img src="cid:part1.07080404.02010003@jlab.org" alt="">
    <pre>
</pre>
    <pre class="moz-signature" cols="72">-- 
Arne Freyberger
Director of Accelerator Operations
Jefferson Lab             
12000 Jefferson Avenue      Cell: (757) 876-6289
Postal Suite 19             Email:  <a class="moz-txt-link-abbreviated" href="mailto:freyberg@jlab.org">freyberg@jlab.org</a> 
Newport News, VA 23606  </pre>