<html><head><meta http-equiv="content-type" content="text/html; charset=utf-8"></head><body dir="auto"><div>An useful link from Steve:</div><div><br></div><div><a href="https://accweb.acc.jlab.org/calendar/view-outlook?year=2015&week=19">https://accweb.acc.jlab.org/calendar/view-outlook?year=2015&week=19</a><br><br>Sent from my iPhone</div><div><br>On Apr 28, 2015, at 3:36 PM, Alex Bogacz <<a href="mailto:bogacz@jlab.org">bogacz@jlab.org</a>> wrote:<br><br></div><blockquote type="cite"><div>
<meta content="text/html; charset=windows-1252" http-equiv="Content-Type">
<div class="moz-cite-prefix"><br>
</div>
<pre wrap="">Dear All,
Here it is....a chronological beam study list for 5/4-18, as we discussed it this afternoon:
- SR compensation coils, hardware check & calibration (4h) (Tief) 5/4
- Cross-talk test (4h) (Jay) 5/4
- Large Dynamic Aperture Diagnostic Stations work (Joe Gubeli, Kevin Jordan)
Part I -tunnel access (4h) 5/4
Part I<i>I</i> - instrumentation work (4h) 5/7
Part I<i>II</i> - instrumentation work (4h) 5/13
- autoquad commissioning with beam (4) (Michele) 5/5
- phaser commissioning with beam (4h) (C. Slominski) 5/5
- ITV system commissioning with beam (4h) (J. Krotze) 5/5
- Energy/cavity calibrations (Jay)
Part I (10h) 5/6
Part II (10h) 5/14
- Injector beam co-linearity test (6h) (Alicia et al) 5/8
- Injector procedure check (4h) (Alicia) 5/8
- Spr/Rec tuning procedure improvements (4h) (Yves) 5/8
- RTI test (6h) (Mahmoud) 5/11
- Dogleg focusing study (6h) (Tief) 5/12
I hope I caught it all. Thanks.