Schedule for PSS certification was just elogged.   Injector lockup July 
19 and 20.  Weekend is clear.
IndexNext>>
COMMENT ON CEBAF / Halls PSS Certification - Spring 2018
Lognumber 3579977. Submitted by jkowal on Fri, 07/06/2018 - 10:46.
The PSS Certification is one week away.
Lockup of tested segments each day around 3pm.
Slight change of the test plan as follows:
16 - Halls A, B, C
17 - S. Linac, BSY, Halls A, B, C
18 - S. Linac, N. Linac, Injector
19 - N. Linac, Injector
20 - Hall D, Tagger, RadCon - all segments
23 - Repairs, retests as necessary
24 - 26 - All segments, complete machine
27 - Repairs/retests as necessary
    
    