[Clas12_calcom] Engineering Run Part #2

Francois-Xavier Girod fxgirod at jlab.org
Wed Jan 3 00:12:56 EST 2018


Dear all

I would like to reiterate a call to individuals who intend to perform
detector calibration, for a definition of skim information in the following
form :

- a list of all the banks you need, ideally something like this :
"RUN::rf","RUN::config", "TimeBasedTrkg::TBTracks", "ECAL::clusters", ...
- a condition on selecting events, ideally a list of consecutive cuts to
apply to variables from specified bank variables. In principle this is
quite arbitrary, and we can define as elaborated conditions for your
skimming strategy as necessary

I will produce the skim files for you, using our golden runs, which will
facilitate and unify the calibration process

Looking forward to your input

Best regards
FX

On Tue, Jan 2, 2018 at 9:42 AM, Daniel Carman <carman at jlab.org> wrote:

> Folks,
>
> Work is getting underway to revisit the CLAS12 Commissioning Plan to
> review what
> steps have been fully (or sufficiently) completed, what steps were
> partially completed,
> and what steps are still left to begin. I would like to update the
> Commissioning Plan to
> lay out a roadmap for the remainder of our commissioning beam time for the
> second
> half of the Engineering Run nominally scheduled for Jan. 12-30, 2018.
>
> We have been maintaining a spreadsheet of the run list from the December
> portion
> of the Engineering Run at:
> https://docs.google.com/spreadsheets/d/1frfBlq51qDXZD6fW5rcR
> efNXSGdVvdMozKUlAVNoUGc/edit?usp=sharing
> This list details the conditions under which the data was taken. In order
> to proceed to
> develop a complete plan for the remainder of our commissioning period, I
> would like
> all subsystem teams to communicate what conditions remain to be studied
> that have
> not yet been addressed to complete the data taking necessary to fully
> characterize their
> subsystems. Please send me complete details this week.
>
> Note that we still have yet to take data for
> 1) the FT due to the hardware issues with the system (that are currently
> being worked on)
> 2) the alignment of the Forward Detectors and Central Detectors at zero
> field
>
> We have already completed a sizable fraction of the Phase 1 beamline
> commissioning
> plan and the Phase 2 CLAS12 commissioning plan as detailed in the existing
> Commissioning
> Plan (these plans are detailed under the “Procedures” column at:
> https://wiki.jlab.org/clas12-run/index.php/Engineering_Run)
>
> It is important for the subsystem teams to look in detail at their
> subsystems through the
> December data to understand their performance in beam. If you have
> questions related to
> the offline cooking or need special data skims, please contact Francois.
> Preliminary data
> investigations and calibrations should be completed with constants entered
> into the ccdb
> during the course of this week. All subsystem teams should have
> representation at the daily
> 10 a.m. analysis meetings to give reports and to provide feedback on their
> detectors. These
> meetings are also important for all of us to understand the priorities for
> completing our
> planned commissioning studies in January.
>
> If you have any questions, please let me know.
>
> Regards,
> Daniel
>
> ************************************************************
> ***********************
> *
>                                         *
> * Dr. Daniel S. Carman                  e-mail : carman at jlab.org
>            *
> * Staff Scientist                              office : (757)-269-5586
> <(757)%20269-5586>                         *
> * Jefferson Laboratory                   web: http://userweb.jlab.org/
> ~carman  *
> *
>                                         *
> ***********************************************************************************
>
>
>
> _______________________________________________
> Clas12_calcom mailing list
> Clas12_calcom at jlab.org
> https://mailman.jlab.org/mailman/listinfo/clas12_calcom
>
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/clas12_calcom/attachments/20180103/aff57c42/attachment.html>


More information about the Clas12_calcom mailing list