[Clas12_calcom] timelines for RGB - Spring19 ready for final checks before pass2
silvia at jlab.org
silvia at jlab.org
Sat May 6 16:10:51 EDT 2023
Dear detector experts,
we just produced timelines for RGB Spring19. From a quick glance,
everything seems ok to me. But could you please check them and confirm
that everything is OK with your subsystem?
This is one of the last steps to proceed with pass2.
The cooking was done with CJ 9.0.0 and the most recent calibrations in CCDB.
Thanks a lot and best regards,
Silvia
More information about the Clas12_calcom
mailing list