Dear CalCom,
after completing beam-offset calibrations, the RGC Winter23 timeline is
done. The link is
https://clas12mon.jlab.org/rgc/Spring2023/pass0v2.02/tlsummary/ and the
recon files are in the directory is
/volatile/clas12/rg-c/productionNew/pass0/mon/v2.02/mon/recon/
I guess the next step is RF calibration? Please let me know.
Thank you all and best regards,
Silvia