[Clas12_calcom] [EXTERNAL] RGA Sp18 Mini timeline available

Daniel Carman carman at jlab.org
Wed Jun 19 01:51:11 EDT 2024


Timothy,

I think the RG-A Spr18 timelines are quite encouraging given the work by Florian to setup initial
DC calibration constants (offsets, t2D parameters) and the work by Raffaella and I to set up the
global timing. The DC calibrations are certainly good enough for me to proceed with FTOF. When
Florian is back in town, he can advance the DC work. For now, I think the next step is to proceed
with the beam offset calibrations and to have Yuri complete the FMT alignment. Let me know.

Regards,
Daniel

On Jun 18, 2024, at 4:13 PM, Hayward, Timothy <timothy.hayward at uconn.edu<mailto:timothy.hayward at uconn.edu>> wrote:

Dear CALCOM,

The mini timelines with all 6 GeV and every tenth 10 GeV run are now available here<https://clas12mon.jlab.org/rga/pass2/sp18/pass0/sp18_v0.10/tlsummary/>. Please let me know if you have any questions.

Best regards,
Timothy

***************************************************************************
*
* Dr. Daniel S. Carman                  e-mail : carman at jlab.org<mailto:carman at jlab.org>
* Staff Scientist                          office : (757)-269-5586
* Jefferson Laboratory                web: http://userweb.jlab.org/~carman
*
***************************************************************************





-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/clas12_calcom/attachments/20240619/666af15f/attachment.html>


More information about the Clas12_calcom mailing list