[Clas12_first_exp] RC summary and no meeting today
mdefurne
mdefurne at jlab.org
Sun Nov 11 12:48:45 EST 2018
Dear all,
Yesterday was not a very productive day. After the issue at the
injector that limited our current at 16nA for part of the owl shift, HV
on a cavity was lost around 11:40am (not the first time it happened). So
MCC took some time to investigate the problem while fixing it. Beam was
back in the Hall only at 8:55pm.
Then, at 9:00pm, we got DAQ issues and Sergey had to go in the Hall
because he could not access remotely some machine: Apparently there is a
bad network switch which needs to be replaced on Monday (bethsw10... I
think it is also the one responsible of the communication loss with
HVECAL2 last wednesday).
11:00pm, Beam is back and DAQ ready, so production is resumed. So far,
things run quite smoothly.
Tomorrow, during the RF recovery, the Hall will be in controlled access
starting at 8:00am: There will be work/studies on solenoid, the network
switch replacement. Eugene will also do a walkthrough.
We should get the beam back early in the afternoon (1pm-2pm is fairly
optimisitic).
Today there will be no meeting. Do not miss the run coordinator report
at the Hall B meeting tomorrow,
Kind regards,
Maxime