[Clas12_rich] RICH cooling, interlocks and assembly structure
Brian Eng
beng at jlab.org
Thu May 5 10:43:35 EDT 2016
For the RICH guys/gals,
Can you send us the model of the LV & HV supplies you're using so that we can see what types of interlocks we can use for them?
Thanks
> On May 5, 2016, at 10:29 AM, George Jacobs <jacobsg at jlab.org> wrote:
>
> Please find attached pdf file showing the cooling circuit and explaining the associated power supply interlocks.
>
> This is a preliminary diagram since system min/max operating parameters have yet to be determined.
>
> George
>
> On 5/3/2016 1:09 PM, Tyler Lemon wrote:
>> Dear Marco Mirazita,
>>
>> We held a short meeting among DSG members to discuss RICH gas and cooling system, interlock system, and anchoring the assembly structure. We discussed the following:
>>
>> Gas and Air Compressor Cooling System:
>> George will create a scheme for the air compressor cooling and send it to Saptarshi Mandal and Ron Bartek for ASME approval. We will also compile a list of components to be purchased (e.g. compressors, tanks, fittings) and the price quote for each component.
>>
>> Interlock System:
>> We have received Valery’s suggestions on the interlock system and as in my previous email, please let us know of any other interlocks would be required. For the hardware interlocks, we will develop a cRIO-based system identical to the SVT interlock system that Peter developed. There will also be software interlocks for alarm handling and controls in EPICS. We will compile a list of all components to be purchased (e.g. cRIO system, monitoring sensors) and the price quote for each component.
>>
>> Assembly Structure:
>> To anchor the assembly structure in EEL 124, George informed us that we will be able to drill holes and anchor the structure to the floor. What size bolts would be used to anchor the structure? Also, is there an engineering drawing for the assembly structure that specifies the lift points for the structure and the bolt size? Please let us know. The drawing would need to be reviewed by Hall B Engineering because of the bolt size and each lift will be an engineered list.
>>
>> Please let us know about the engineering drawings and where we could find them. Thank you in advance.
>>
>> Best Regards,
>> Tyler
>>
>> _______________________________________________
>> Clas12_rich mailing list
>> Clas12_rich at jlab.org
>> https://mailman.jlab.org/mailman/listinfo/clas12_rich
>
> --
> George Jacobs
> Jefferson Lab (TJNAF)
> STE 12
> 12000 Jefferson Ave.
> Newport News, VA 23606
>
> (office) 757-269-7115
>
> (cell) 757-876-0480
>
> (email) jacobsg at jlab.org
>
> (website) https://userweb.jlab.org/~jacobsg
>
> <RICH-AirCooling-PS-Interlocks.pdf>_______________________________________________
> Clas12_rich mailing list
> Clas12_rich at jlab.org
> https://mailman.jlab.org/mailman/listinfo/clas12_rich
More information about the Clas12_rich
mailing list