[Clas12_rich] Planned optical measurements of mirrors in first week of October
Tyler Lemon
tlemon at jlab.org
Thu Sep 29 17:03:11 EDT 2016
Dear Marco,
For the optical measurements that are planned for the first week of October, the two optical tables are unavailable until the end of November. I talked to Brian to confirm this and the tables are needed for SVT repairs that are happening now .
However, we should be able to repeat the spot tests with the mirror on a regular table, as before, and a second regular table for the CCD stand. Please let us know if this lay out works for these optical measurements so we can prepare the clean room.
Best regards,
Tyler
From: "Marco Contalbrigo" <mcontalb at fe.infn.it>
To: "Tyler Lemon" <tlemon at jlab.org>
Cc: "clas12 rich" <clas12_rich at jlab.org>, "Patrizia Rossi" <rossi at jlab.org>
Sent: Wednesday, September 28, 2016 4:39:51 PM
Subject: Re: [Clas12_rich] Shipping of RICH spherical mirrors for mounting and final coating
Dear Tyler,
we plan to send them back in October, after a second round of
optical measurements. We plan to measure the mirror again,
hopefully with the complete characterization system, the first
days of October. Marco Mirazita and I will arrive at JLab on
September 30: I will stay till Friday 7 (excluded) and Marco
a bit longer, till the middle of the following week.
Ciao, Marco.
On Wed, 28 Sep 2016, Tyler Lemon wrote:
> Dear Marco Contalbrigo,
>
> Now that all ten spherical mirrors have been delivered and accepted, when would the
> mirrors need to be shipped for the mounting and final reflective coating? We have
> kept the boxes they were shipped to JLab in so they can be re-packed in those boxes
> once their shipment is scheduled.
>
> Best regards,
> Tyler
>
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/clas12_rich/attachments/20160929/f02ad233/attachment.html>
More information about the Clas12_rich
mailing list