[clas_members] shift cancellations

Nathan Baltzell baltzell at jlab.org
Mon Aug 21 12:11:40 EDT 2023


Dear All,

*** The first shifts for RG-D will now be Monday, September 11, day shift.  All prior shifts are cancelled. ***

Current estimates have the accelerator ready for physics on the 5th, starting with beam delivery to C, followed by D, but the new Hall B cryotarget may not be fully ready until the 15th.  Since shifts on the week of the 11th are assigned to locals, we'll keep them active for now.

Regards,
Nathan, PDL




More information about the clas_members mailing list