<html>
  <head>

    <meta http-equiv="content-type" content="text/html; charset=ISO-8859-1">
  </head>
  <body bgcolor="#FFFFFF" text="#000000">
    Dear Colleagues,<br>
    <br>
    See the run status below, <br>
    for your information.<br>
    <br>
    Volker<br>
    <br>
    <br>
    <br>
    -------- Original Message --------
    <table class="moz-email-headers-table" border="0" cellpadding="0"
      cellspacing="0">
      <tbody>
        <tr>
          <th align="RIGHT" nowrap="nowrap" valign="BASELINE">Subject: </th>
          <td>g14 run status</td>
        </tr>
        <tr>
          <th align="RIGHT" nowrap="nowrap" valign="BASELINE">Date: </th>
          <td>Thu, 1 Dec 2011 02:53:31 -0500 (EST)</td>
        </tr>
        <tr>
          <th align="RIGHT" nowrap="nowrap" valign="BASELINE">From: </th>
          <td>Mahbub Khandaker <a class="moz-txt-link-rfc2396E" href="mailto:mahbub@jlab.org">&lt;mahbub@jlab.org&gt;</a></td>
        </tr>
        <tr>
          <th align="RIGHT" nowrap="nowrap" valign="BASELINE">To: </th>
          <td><a class="moz-txt-link-abbreviated" href="mailto:g14_run@jlab.org">g14_run@jlab.org</a></td>
        </tr>
        <tr>
          <th align="RIGHT" nowrap="nowrap" valign="BASELINE">CC: </th>
          <td>Volker Burkert <a class="moz-txt-link-rfc2396E" href="mailto:burkert@jlab.org">&lt;burkert@jlab.org&gt;</a>, Douglas Tilles
            <a class="moz-txt-link-rfc2396E" href="mailto:tilles@jlab.org">&lt;tilles@jlab.org&gt;</a></td>
        </tr>
      </tbody>
    </table>
    <br>
    <br>
    <pre>Dear Collaborators,

Here is an update on the g14 run status as of Wednesday evening:

- The HD "silver" target was successfully transferred from the
  production dewar to the IBC which is in vertical orientation.

- NMR studies were initiated early evening on Wednesday and is
  continuing through the night shift.

- Hall was taken to Controlled Access around 1:00 a.m. in order to
  limit activities around the NMR system when these studies will
  continue on Thursday morning.

Plans for Thursday:

- NMR studies in early morning.
- IBC going to horizontal orientation and prepare for rolling in
  to CLAS.
- Beamline components will be put back and aligned after IBC in CLAS.
- Plan for beam delivery into the hall in late afternoon early evening.