Dear all,<br>
<br>
We had very busy and very productive weekend with beam delivery to
Hall-B tagger dump.<br>
After 30 months, 1 pass CW beam restored to Hall-B tagger dump at
about 9:30am on <br>
November 9, 2014. Please see logbook for details. <br>
<br>
Hall-B was opened at 7am today (to restricted access) and will
remain open in swing on <br>
Friday, November 14. This time will be used to finish work in the
Hall for downstream beamline.<br>
<br>
<b>Shifts over week, from 8am Monday, November 10, till 4pm on
Friday, November 14 are canceled. </b><b><br>
</b><br>
Regards, Stepan<br>
<br>
<br>
<div class="moz-cite-prefix">On 11/7/14 12:13 PM, Stepan Stepanyan
wrote:<br>
</div>
<blockquote cite="mid:545CFDCE.5080003@jlab.org" type="cite">Dear
all,
<br>
<br>
From what we had yesterday things have shifted by one shift.
Machine will start multihall
<br>
separation work swing today. Attached is the shift schedule for
Hall-B as we have it at the
<br>
moment. Evening shifts today are canceled. Depending on how repair
work and HCO will
<br>
go for BSY and Halls we may or may not have night shifts, email
update will follow late
<br>
afternoon.
<br>
<br>
Regards, Stepan