<div dir="ltr"><div>Hi everyone,</div><div><br></div><div>I would like to propose canceling tomorrow's CPS meeting. We will have our next meeting in 2-3 weeks. To give an overview of what has been happening recently: our main focus areas has been to finalize the procurements for the CPS and many of us are working on different aspects related to that. Please see below an overview of the items that need to be procured. The items are:<br><ul><li><b>Borated poly </b>(~$25k)</li><ul><li>
We can buy the borated polyflo (5% borated) as thin sheets such that we 
can easily bend it as needed given the shape of the CPS shielding. Steve
 will need to make a shelf/container for the bottom part as the rest of 
the CPS weight will sit on top of it

</li></ul><li><b>Cu absorber</b> (~$25k, but may increase)</li><ul><li>We can buy the Cu absorber once the design and test is complete, 
expected later this FY. We do have concerns that the material costs have
 gone quite a bit up here. But we are overall okay with the CPS costs as
 we have saved on expensive 
shielding by redoing the design so need less additional shielding costs 
than originally projected.



</li></ul><li><b>Additional W/Cu inserts</b> ($100k-$150k)</li><ul><li>We need more W/Cu - inserts, machinable, so we can use it to machine in a slot to surround the outgoing beam pipe


</li></ul><li> <b>Additional tungsten bricks</b> ($0k-$100k)</li><ul><li>
We may need up to 50 additional tungsten shielding blocks. We will know 
once we have checked with the radiation model simulation. 



</li></ul><li><b>Support structure</b> ($200k)</li><ul><li>
Steve may need a support, pending on where we are with those drawings, 
as we need to complete in FY23. In principle, we can call the CPS 
without support a complete capital equipment project, but since we are 
still well within budget we can fold it in (if ready).

</li></ul></ul>The bottom line is $450k including the support structure and about $250k without it. <br><br><div>We
 hopefully soon have PRs for the borated poly (Bogdan), for the 
remaining W bricks and/or W-Cu (Bogdan), and then we need PRs for the Cu
 absorber (Steve) and pending where we are for the platform 
(Steve/Paulo). <br></div><div><br></div><div>Best wishes,</div><div>Tanja<br></div>