I will not be in this morning but hope to be able to check emails from time to time.  Things we have to do today:

1. Get roughing pumps hooked up to the vert line.
2. Test interlock trip point for nitrogen flow (Wilson, Sun)
3. Install shielding around Moeller dump.  Ron Lassiter is working on completing the drawings for this for Vashek to sign. A draft version is attached. This design requires 13 concrete blocks, 89 full size bricks, two half sized bricks, and the machine bricks that were painted yesterday.  The bricks at 4F00 can be used if necessary. The half size bricks are on the IR wiggler.
4. Find a way to drive the pico motors for the ultra viewer and use it to try to center in the target aperture.
5. Check the MO distribution to look for loose connections or bad cables.
6. Analyze emittance data to figure out the Twiss parameters going into the 4F.
7. Figure out cause of zone 2 trips. This happened twice yesterday and at least once the day before.
8. Verify sign off of OSP 62129 (target OSP)  Ed Douberly still had to sign off on it yesterday afternoon.
9.  Need some detective work on IOCFEL10.  I remember that the software group had installed some diagnostic software on this IOC.  Is it still there and did it catch anything?
10. Check the trigger for ITV5F05.  It is very flaky and comes and goes.  Also should check ITV5F07.  We did not see anything on that viewer.

Steve Benson
-------------- next part --------------
A non-text attachment was scrubbed...
Name: rlassit_JL0039139---dwg1.pdf
Type: application/pdf
Size: 1882202 bytes
Desc: not available
URL: <https://mailman.jlab.org/pipermail/dlsupport/attachments/20160826/92f0c7d3/attachment-0001.pdf>


More information about the Dlsupport mailing list