Hi Dave,
We haven't powered any of the 4F quads yet. That will not happen
until the spool pieces are installed due to splitting of the magnet. We
have to perform a voltage/ current/ polarity measurement of any magnet
as part of the HCO. I'll make sure LCW gets put on the skews.
-Jim
On 7/5/2016 10:08 AM, David Douglas wrote:
>
> re: #2) - please put the results of the test into the LERFLog. Thanks
>
> D
>
>
> On 7/5/2016 10:07 AM, David Douglas wrote:
>>
>> Hi Jim - don't know if the following was communicated to you or not, but
>>
>> 1) Steve asked if the 10 additional skew quads needed water cooling.
>> Answer: if the other quads are run with water cooling, these will
>> need it as well. They run at the same fields as the normal quads.
>>
>> 2) Has each quad been polarity checked (i.e. a Hall probe put on each
>> pole of each quad)? We need to be sure there are consistent sign
>> conventions through 4F, and I'll need to know what pole of each quad
>> is at what sign and field level when the usual +5A test current is
>> being run.
>>
>> Thanks,
>> DD
>>
>>
>> On 6/30/2016 4:32 PM, Jim Coleman wrote:
>>> apologies for sending it out late
>>>
>>>
>>>
>>> _______________________________________________
>>> Dlsupport mailing list
>>> Dlsupport at jlab.org
>>> https://mailman.jlab.org/mailman/listinfo/dlsupport
>>
>>
>>
>> _______________________________________________
>> Dlsupport mailing list
>> Dlsupport at jlab.org
>> https://mailman.jlab.org/mailman/listinfo/dlsupport
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dlsupport/attachments/20160705/85714765/attachment.html>
More information about the Dlsupport
mailing list