I have attached the latest task schedule.  This modifies a couple tasks and adds a few new ones.  Last week was quite productive (see attached photo)

Progress in the last week:

Breaker ordered.
Shielding Blocks removed.
Wiggler and THz chicane removed along with support stands and grout.
Removed 4F09 and 4F03 stands and girders
Marked floor bolt positions for skew quad stands
Released rev- nomenclature document
Agreed on vacuum interlock strategy
Started to lay out vacuum chambers
P&ID update released
Met to discuss detector chamber installation and alignment
Good progress on detailing the LED

Tasks this week:

Remove 3 quads and modify to mount as skew quads (start).
Install skew quad stands
Lay out solenoid rail plate position on the floor
Complete power supply shuffle (Power outage)
Work out trim supply layout
Get E-BPM computer up and running.
Get the rest of the beam physics data into the LED

Notes:
1.  HUGS tour June 3rd at 9:55 for 30 minutes.
2. LERFDL active for detector installation work.

Steve Benson
-------------- next part --------------
A non-text attachment was scrubbed...
Name: Ready for DarkLight, lores.jpg
Type: image/jpg
Size: 67577 bytes
Desc: not available
URL: <https://mailman.jlab.org/pipermail/dlsupport/attachments/20160523/08c866ee/attachment-0001.jpg>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: TaskList_05_24_2016-sm.xlsx
Type: application/vnd.openxmlformats-officedocument.spreadsheetml.sheet
Size: 2783000 bytes
Desc: not available
URL: <https://mailman.jlab.org/pipermail/dlsupport/attachments/20160523/08c866ee/attachment-0001.xlsx>


More information about the Dlsupport mailing list