[dsg-eic_dirc] Estimated Gantt chart for DSG and EIC DIRC
Tyler Lemon
tlemon at jlab.org
Wed Jun 21 16:56:54 EDT 2023
Hello,
Attached is Gantt chart showing DSG's planned work on EIC DIRC through September 30.
All task durations are estimated and do not have any additional contingency time added in.
Also, the schedule assumes that the detector components will be delivered in late September 2023. This was based on a 3-month delivery time approximation given in the the last DSG EIC DIRC meeting. Any shifts in detector component delivery will change the overall time line.
If there are any questions, just let me know.
-Tyler
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-eic_dirc/attachments/20230621/b656b2a5/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: EIC DIRC schedule 2023-06-20.xlsx
Type: application/vnd.openxmlformats-officedocument.spreadsheetml.sheet
Size: 27320 bytes
Desc: EIC DIRC schedule 2023-06-20.xlsx
URL: <https://mailman.jlab.org/pipermail/dsg-eic_dirc/attachments/20230621/b656b2a5/attachment-0001.xlsx>
More information about the dsg-eic_dirc
mailing list