Hi Bogdan,

I spoke with Albert yesterday and he informed me that springs are being procured. Assembly production will stop next week until the new springs arrive. DSG will continue some of the preparation steps (measuring lead-glass blocks, sorting, cutting foils, and light-guide wrapping) until there are enough to make all the supermodules.

In addition to the springs, we will need at least 5 more frames to reach 57 supermodules and 6 lead-glass/light-guide assemblies to have the minimum amount to make 57 supermodules plus some spare lead-glass/light-guide assemblies.

Regards,
Marc

Part name       parts on-hand   will make # Supermodules        comment
cut springs     45      5       limiting factor on supermodule production
cu clad lead glass/light guide assembly 375     41      need 9 more

SM 1 frames     18      18      need 3 frames
SM 2 frames     19      19      need 2 frames
total frames    37      37      need to make 42 sm

Completed Supermodules
SM 1    7
SM 2    8
subtotal        15

Supermodules needed to complete (57 total)      42






-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-halla_ecal/attachments/20220201/0e8b5072/attachment-0001.html>


More information about the Dsg-halla_ecal mailing list