[Dsg-halla_ecal] ECAL heater controls update
Marc Mcmullen
mcmullen at jlab.org
Mon Apr 7 15:15:59 EDT 2025
Hi Don,
Since the system is up and running and will be that way for awhile, the controls software and system will stay in this configuration. We are not planning any other software changes for now.
I will contact you when the new Omegas arrive and coordinate that installation during a shutdown period.
Regards,
Marc
________________________________
From: Donald Jones <jonesdc at jlab.org>
Sent: Monday, April 7, 2025 9:19 AM
To: dsg-halla_ecal at jlab.org <dsg-halla_ecal at jlab.org>; Marc Mcmullen <mcmullen at jlab.org>
Subject: Re: ECAL heater controls update
Hi Marc, Brian,
I started the heaters this morning. The GUI is working well. The power output is great. Thanks for the upgrades that allowed this power increase.
-Dopn
Donald Jones
Hall A/C Staff Scientist
Jefferson Lab
Newport News, VA
________________________________
From: Dsg-halla_ecal <dsg-halla_ecal-bounces at jlab.org> on behalf of Marc Mcmullen via Dsg-halla_ecal <dsg-halla_ecal at jlab.org>
Sent: Friday, April 4, 2025 5:26 PM
To: dsg-halla_ecal at jlab.org <dsg-halla_ecal at jlab.org>
Subject: [Dsg-halla_ecal] ECAL heater controls update
Hi Don,
We have completed some hardware and software updates to the system and the system is available for heating.
The cooled volume pressure has been added and we have added an an extra module for the control voltages. There are a maximum of 13 control voltage channels for each module, the last one has 9 channels.
We have added some of the EPICS process variable which I believe you have requested archival. The EPICS will still need some work done on both the heated and cooled middle temperature signals. All of these can be viewed on the GUI, we just need to get the plotting and archiving going.
The top heated volume sensor, the cooled volume pressure, and the cooled volume sensor can be monitored through EPICS.
You will have the latest GUI update on the desktop which has indicators for the new pressures, and enclosure temperature signals. I'll put that on by 5:30 today.
I will update the mailing list with any progress.
-Marc
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-halla_ecal/attachments/20250407/5460c7e4/attachment.html>
More information about the Dsg-halla_ecal
mailing list