Hi Nilanga, Kondo, and Everisto,
George has completed the preliminary P&I for the distribution panel and a components list (see attachments). If everyone can take some time to review the documents and provide comment, we can move forward with mechanical drawings and procurement. If all interested parties can send comments to this email list, I will compile them and we can meet in January to have a discussion.
Before we start procurement, Jack, Brad, and the design authority will need to approve of the design/components.
If there has been any significant progress on the development of the detectors, please send an update to this email list, so that we may stay abreast of the advancements.
Regards,
Marc
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-halla_gas/attachments/20191216/5e63694d/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: HallA-GEM-GAS-Distro-2Panel-version-P&I.pdf
Type: application/pdf
Size: 164586 bytes
Desc: HallA-GEM-GAS-Distro-2Panel-version-P&I.pdf
URL: <https://mailman.jlab.org/pipermail/dsg-halla_gas/attachments/20191216/5e63694d/attachment-0002.pdf>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: HallA-GEM-GAS-Distro-Components-25Sept2019.pdf
Type: application/pdf
Size: 324095 bytes
Desc: HallA-GEM-GAS-Distro-Components-25Sept2019.pdf
URL: <https://mailman.jlab.org/pipermail/dsg-halla_gas/attachments/20191216/5e63694d/attachment-0003.pdf>
More information about the Dsg-halla_gas
mailing list