[Dsg-halla_gas] Hall A Gas Distribution Meeting Minutes
Jack Segal
segal at jlab.org
Tue Aug 18 12:03:56 EDT 2020
Thanks, Tyler. Sorry I missed it. I had a dental appointment. I forgot about this meeting.
On 8/18/2020 12:01 PM, Tyler Lemon wrote:
> Hello Jack,
>
> Attached are the slides I presented in the meeting.
>
> We wanted to include the slides with the meeting minutes since some of them apply to the rack and gas panel layout. If you have any questions, just let us know.
>
> Just a note, though: the chassis design is still in progress and will probably change before it is finalized.
>
> Thanks,
> Tyler
> ---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
> *From:* Dsg-halla_gas <dsg-halla_gas-bounces at jlab.org> on behalf of Marc Mcmullen <mcmullen at jlab.org>
> *Sent:* Tuesday, August 18, 2020 11:57 AM
> *To:* dsg-halla_gas at jlab.org <dsg-halla_gas at jlab.org>
> *Subject:* [Dsg-halla_gas] Hall A Gas Distribution Meeting Minutes
> Hi,
>
> The minutes from today's meeting on the GEM gas distribution system are attached.
>
> Regards,
> Marc
>
> _______________________________________________
> Dsg-halla_gas mailing list
> Dsg-halla_gas at jlab.org
> https://mailman.jlab.org/mailman/listinfo/dsg-halla_gas
>
--
John(Jack) Segal
Halls A and C Spectrometer Support Manager
Thomas Jefferson National Accelerator Facility
12000 Jefferson Avenue
Suite 12
Newport News, VA 23606-4486
Phone: (757) 269-7242
Cell: (757) 320-9977