Below is the link for the presentation on timeline I gave about 2.5 weeks ago. The timelines are specifically on slides #2 and #3 and we are still on schedule today based on that timeline.
====
https://hallaweb.jlab.org/wiki/images/d/d6/20210630_meeting.pdf
====
For the activities, I assume you want to know about our need for the EEL124 clean room. So basically slides #1 and #3 summarized what are left to be done and this will push us to mid to end August for the clean room occupancy.

Please let me know if you need additional or specific info
Best regards
Kondo

From: Marc Mcmullen <mcmullen at jlab.org>
Sent: Friday, July 16, 2021 6:35 AM
To: Brad Sawatzky <brads at jlab.org>; Kondo Gnanvo <kagnanvo at jlab.org>; Gnanvo, Kondo (kg6cq) <kg6cq at virginia.edu>
Cc: dsg-halla_gem at jlab.org
Subject: Re: [EXTERNAL] Re: [Dsg-halla_gem] SBS GEM progress

Hi Kondo,

Can you send an update on the SBS activities and a timeline? Brad mentioned that you had given a presentation in June. Could you send a copy of the talk, as well.

Regards,
Marc

________________________________
From: Brad Sawatzky <brads at jlab.org<mailto:brads at jlab.org>>
Sent: Friday, July 2, 2021 11:31 AM
To: Kondo Gnanvo <kagnanvo at jlab.org<mailto:kagnanvo at jlab.org>>; Marc Mcmullen <mcmullen at jlab.org<mailto:mcmullen at jlab.org>>
Cc: dsg-halla_gem at jlab.org<mailto:dsg-halla_gem at jlab.org> <dsg-halla_gem at jlab.org<mailto:dsg-halla_gem at jlab.org>>
Subject: [EXTERNAL] Re: [Dsg-halla_gem] SBS GEM progress


Kondo, can you send a copy of the summary slides from last Wednesday,
along with some estimated dates for when the SBS layers are planned
to be ready in the EEL, and when (best estimate) they would be moved to
the Hall.

Marc, I assume you're mostly wondering about when you'll be needing to
set up and test the full gas distribution system, correct?

-- Brad

On Fri, 02 Jul 2021, Marc Mcmullen wrote:

> Hi Kondo and Brad,
> Can you provide an update on the progress of the SBS GEM assembly?
> Regards,
> Marc

--
Brad Sawatzky (he/him), PhD <brads at jlab.org<mailto:brads at jlab.org>> -<>- Jefferson Lab/ Hall C/C111
Ph: 757-269-5947  -<>-  Fax: 757-269-5235  -<>- Pager: brads-page at jlab.org<mailto:brads-page at jlab.org>
The most exciting phrase to hear in science, the one that heralds new
  discoveries, is not "Eureka!" but "That's funny..."   -- Isaac Asimov
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-halla_gem/attachments/20210716/a8e48daa/attachment-0001.html>


More information about the Dsg-halla_gem mailing list