[Dsg-halla_gem] EEL Large Clean Room Air Handler Maintenance
Yuri Gotra
gotra at jlab.org
Tue Mar 30 11:05:54 EDT 2021
Thank you Marc,
No scheduling issue for the CVT.
On 3/30/21 11:01 AM, Marc Mcmullen wrote:
>
> Hi Brad and Yuri,
>
> Tomorrow (9am) facilities management is planning a preventative
> maintenance of the clean room’s air handlers. They will change
> filters, check belts and ensure everything is working as it should.
>
> The air handler will be down starting at 9am for about an hour.
>
> Please ensure the roll up doors are down after work is completed
> today. There should be no work done during the maintenance. Please
> notify me if there is a scheduling issue.
>
> Regards,
>
> Marc McMullen
>
> Sr. Instrumentation Designer
>
> Detector Support Group
>
> (757) 269-7738
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-halla_gem/attachments/20210330/863401cc/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: gotra.vcf
Type: text/x-vcard
Size: 102 bytes
Desc: not available
URL: <https://mailman.jlab.org/pipermail/dsg-halla_gem/attachments/20210330/863401cc/attachment.vcf>
More information about the Dsg-halla_gem
mailing list