Hello Steven,

Here is an status report for the tasks in which DSG is involved:

PLC programming

Cooldown and JTV control (For CCR and HX) routines are under revision.
Spreadsheet with PID parameters for each JT valve is in progress
MPS communication, controls and monitoring PLC code will be same as the already implemented PLC from HMS PSU.
Testing of PLC code will be done during commissioning of the magnet

HMI System
6 screens (first versions) completed an under review. Preliminary test completed, final test will be done during commissioning.
3 screens under development (CCR expert, JT Valve Page, Cooldown screens)
Development of the FT VIew data logger completed and tested on DSG PLC test station. We only need to decide the PLC tags that will be logged.

Hardware - Instrumentation
CCS board: One of six boards is assembled, board components are at the lab, planning assembly of remain boards in the next weeks.
Motor Controller Relay board: Altium design completed. Bare boards and part being ordered.

Electrical Drawings
Wire Cable Diagrams drawings for temperature, voltage taps and load cells need to be modified based on the vacuum feed through pins changes, once we're back on the Lab.
Completed modifications of JT Valve drawings based new PLC channel module's channels assignment.
Completed drawings with agreed modifications can be found at : https://www.jlab.org/physics/dsg/technical_documentation/hall_a/drawings

Documentation
Completed Network, Control and Instrumentation Overview diagram.


You can find our DSG Tasks tracking spreadsheet with more information at: https://www.jlab.org/div_dept/physics_division/dsg/technical_documentation/Hall_A/SoLID/DSG-HallA-SoLID_Magnet_I&C_tasks_status_v12_07-02-2020.xlsx


More details about the status of the related tasks can be discussed during our next meeting.

Have a nice weekend,
Pablo

________________________________
From: Steven Lassiter <lassiter at jlab.org>
Sent: Wednesday, July 1, 2020 9:34 AM
To: Pablo Campero Rojas <campero at jlab.org>; dsg-halla_magnets at jlab.org <dsg-halla_magnets at jlab.org>
Subject: Re: video meeting today?

Ok,

Can someone send me an update schedule for the controls? HMI development, software, I/O rack layout, build and test?

Thank you
Steven
________________________________
From: Pablo Campero Rojas <campero at jlab.org>
Sent: Wednesday, July 1, 2020 9:31 AM
To: Steven Lassiter <lassiter at jlab.org>; dsg-halla_magnets at jlab.org <dsg-halla_magnets at jlab.org>
Subject: Re: video meeting today?

Hi Steven,

There is not Bluejeans meeting today.

Pablo
________________________________
From: Dsg-halla_magnets <dsg-halla_magnets-bounces at jlab.org> on behalf of Steven Lassiter <lassiter at jlab.org>
Sent: Wednesday, July 1, 2020 8:34 AM
To: dsg-halla_magnets at jlab.org <dsg-halla_magnets at jlab.org>
Subject: [Dsg-halla_magnets] video meeting today?

Hello

 Will there be a video call today?

Steven
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-halla_solid/attachments/20200702/035bf117/attachment-0002.html>


More information about the Dsg-halla_magnets mailing list