[Dsg-halla_magnets] Power Supplies for Cleo

Pablo Campero Rojas campero at jlab.org
Wed Apr 27 11:53:45 EDT 2022


Hello Steven,

Can you list the tasks that need to be done with the power supply for the 100 A test.

Are we going to read the output current of the power supply in the PLC?
Will we use an external device to measure the power supply current?
Is any remote monitoring/control of the power supply status planned?


--Pablo
________________________________
From: Dsg-halla_magnets <dsg-halla_magnets-bounces at jlab.org> on behalf of Steven Lassiter <lassiter at jlab.org>
Sent: Tuesday, April 26, 2022 4:14 PM
To: dsg-halla_magnets at jlab.org <dsg-halla_magnets at jlab.org>
Subject: [Dsg-halla_magnets] Fw: Power Supplies for Cleo

Hi,

 Here is the manual for the PSU that is being planned to be used for the CLEO-II magnet test run.

Steven
________________________________
From: Ellen Becker <ebecker at jlab.org>
Sent: Monday, April 25, 2022 11:25 AM
To: Steven Lassiter <lassiter at jlab.org>
Subject: Re: Power Supplies for Cleo

+/- 30V and +/-125A

Also, they run off 208VAC.

Attaching the manual.
________________________________
From: Steven Lassiter <lassiter at jlab.org>
Sent: Monday, April 25, 2022 11:22 AM
To: Ellen Becker <ebecker at jlab.org>
Subject: Re: Power Supplies for Cleo

What is the max max current and voltage output per supply?

thanks
Steven
________________________________
From: Ellen Becker <ebecker at jlab.org>
Sent: Monday, April 25, 2022 11:15 AM
To: Steven Lassiter <lassiter at jlab.org>
Subject: Power Supplies for Cleo

Hi Steve,

Jack had me replace the capacitors in a couple Lakeshore 622 superconducting magnet power supplies, and then test them for use in the Cleo magnet testing. I ran both supplies up to 50A with a short across the output and double checked them with a DC current clamp meter. One supply (the bottom one in the picture) ran exactly at the commanded setpoint, 50A at 50A, the other ran at 50.8A at 50A setpoint (and the error scaled with the setpoint). I think that should be sufficient for the Cleo testing, so I brought them over to the Test Lab, and Jack said I should let you know they are ready for you. I attached a picture of where I left them.

Ellen
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-halla_solid/attachments/20220427/1c686331/attachment-0002.html>


More information about the Dsg-halla_magnets mailing list