[Dsg-dc] DCGAS line installation in Hall B (Critical Path Items)
burkert
burkert at jlab.org
Wed Dec 14 11:07:45 EST 2016
Amrit, the KPP run officially starts on February 3. However, we are
aiming to be ready for beam one week earlier.
Volker
On 12/14/16 10:44 AM, Amrit Yegneswaran wrote:
> hello,
> as we don't have a DC logbook, is there a way anyone sees how to
> inform each other as soon as the job is done.
> given the x'mas bonhomie today in the afternoon, the day is
> essentially done.
> and lord knows why everyone was unhappy with Nero.
> amrit
> ps. do we have a date for the start of KPP.
> george and marc have come up with a schedule, which will be sent out
> tomorrow after we discuss a few minor points in the dsg meeting.
>
> ------------------------------------------------------------------------
> *From: *"Bob Miller" <rmiller at jlab.org>
> *To: *"George Jacobs" <jacobsg at jlab.org>
> *Cc: *"Dave Kashy" <kashy at jlab.org>, "Mac Mestayer"
> <mestayer at jlab.org>, "Volker Burkert" <burkert at jlab.org>, "Stepan
> Stepanyan" <stepanya at jlab.org>, "Glenn Young" <gyoung at jlab.org>,
> "Amrit Yegneswaran" <yeg at jlab.org>, "Patrizia Rossi" <rossi at jlab.org>
> *Sent: *Wednesday, December 14, 2016 10:08:44 AM
> *Subject: *Re: DCGAS line installation in Hall B (Critical Path Items)
>
> You can start right now George. The additional cable tray that we
> discussed was installed yesterday.
>
> Regards,
>
> Bob
>
>
> On 12/14/2016 10:07 AM, George Jacobs wrote:
>
> Hi Bob,
>
> When can we start this critical path job? This is for running the
> following lines from the DCGAS valve panel on L3 space frame to
> the manifolds on the torus.
>
> The following line need installed, connected, and tested.
> R1 Supply line
> R2 Supply line
> R3 Supply line
> R1-2 Return line
> R3 Return line
> R1-2 DPT line
> R3 DPT line
> R1-2 Endplate N2 Purge Supply line
> R3 Endplate N2 Purge Supply line
>
> Has the cable tray been installed for routing these gas lines? If
> not, can we run the lines first and then install the tray later?
>
> Let me know ASAP when we can start this job. Time is running out.
> Even if only some of the TORUS manifolds are in place, we can at
> least start this job.
>
> I have attached the DC Gas System critical path document.
>
> Thanks,
> George
>
>
> --
> George Jacobs
> Jefferson Lab (TJNAF)
> STE 12
> 12000 Jefferson Ave.
> Newport News, VA 23606
>
> (office) 757-269-7115
>
> (cell) 757-876-0480
>
> (email)jacobsg at jlab.org
>
> (website)https://userweb.jlab.org/~jacobsg
>
>
> --
> Bob Miller
> Hall B Lead Engineer
> Jefferson Lab
> 757 269-7867
>
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-dc/attachments/20161214/073fa56c/attachment.html>
More information about the Dsg-dc
mailing list