[Dsg-dc] DCGAS line installation in Hall B (Critical Path Items)

Mac Mestayer mestayer at jlab.org
Wed Dec 14 10:51:50 EST 2016


Hello Amrit;

It's because he fiddled while Rome burned, and on the
2nd point: we do have a DC logbook, hbdc, at
https://logbooks.jlab.org/book/hbdc
I set it up about a month ago.

For communication, though, this email list is good.

 			- Mac


"mestayer at jlab.org", (757)-269-7252

On Wed, 14 Dec 2016, Amrit Yegneswaran wrote:

> hello,
> as we don't have a DC logbook, is there a way anyone sees how to inform each other as soon as the job is done.
> given the x'mas bonhomie today in the afternoon, the day is essentially done.
> and lord knows why everyone was unhappy with Nero.
> amrit
> ps. do we have a date for the start of KPP.
> george and marc have come up with a schedule, which will be sent out tomorrow after we discuss a few minor points in the dsg meeting.
>
>
> From: "Bob Miller" <rmiller at jlab.org>
> To: "George Jacobs" <jacobsg at jlab.org>
> Cc: "Dave Kashy" <kashy at jlab.org>, "Mac Mestayer" <mestayer at jlab.org>, "Volker Burkert" <burkert at jlab.org>, "Stepan Stepanyan" <stepanya at jlab.org>, "Glenn Young" <gyoung at jlab.org>, "Amrit Yegneswaran" <yeg at jlab.org>, "Patrizia Rossi" <rossi at jlab.org>
> Sent: Wednesday, December 14, 2016 10:08:44 AM
> Subject: Re: DCGAS line installation in Hall B (Critical Path Items)
>
>
>
> You can start right now George. The additional cable tray that we discussed was installed yesterday.
>
> Regards,
>
> Bob
>
> On 12/14/2016 10:07 AM, George Jacobs wrote:
>
>
> Hi Bob,
>
> When can we start this critical path job? This is for running the following lines from the DCGAS valve panel on L3 space frame to the manifolds on the torus.
>
> The following line need installed, connected, and tested.
> R1 Supply line
> R2 Supply line
> R3 Supply line
> R1-2 Return line
> R3 Return line
> R1-2 DPT line
> R3 DPT line
> R1-2 Endplate N2 Purge Supply line
> R3 Endplate N2 Purge Supply line
>
> Has the cable tray been installed for routing these gas lines? If not, can we run the lines first and then install the tray later?
>
> Let me know ASAP when we can start this job. Time is running out. Even if only some of the TORUS manifolds are in place, we can at least start this job.
>
> I have attached the DC Gas System critical path document.
>
> Thanks,
> George
>
>
> -- 
> George Jacobs
> Jefferson Lab (TJNAF)
> STE 12
> 12000 Jefferson Ave.
> Newport News, VA 23606
>
> (office) 757-269-7115
>
> (cell)   757-876-0480
>
> (email) jacobsg at jlab.org (website) https://userweb.jlab.org/~jacobsg
>
>
>
> -- 
> Bob Miller
> Hall B Lead Engineer
> Jefferson Lab
> 757 269-7867
>
>



More information about the Dsg-dc mailing list