so marc,
you are implying that all needed components must be in hand by 6/15 to be ready for the 10/17 run.
so, guessing that the lead time to procure typical (usual, common, and reasonable) components is about 2 weeks, the DA should finish his initial analysis by 5/31.
DA initial analysis must finish by 5/31.
procure components 6/1---6/15
fabricate, install and test 6/16-- 10/15
could george and you please improve upon the time line, and e-mail the groups.
amrit
From: "Marc Mcmullen" <mcmullen at jlab.org>
To: dsg-mvt at jlab.org, dsg-ft at jlab.org, "Volker Burkert" <burkert at jlab.org>, "Bob Miller" <rmiller at jlab.org>, "Mac Mestayer" <mestayer at jlab.org>, "Maxime Defurne" <mdefurne at jlab.org>
Cc: "Patrizia Rossi" <rossi at jlab.org>
Sent: Wednesday, April 26, 2017 9:02:21 AM
Subject: [Dsg-mvt] Emailing - Requirements to complete gas service for the MVT to CLAS12.pdf
Good Morning,
Attached are the requirements to complete the gas service for the MVT to
operate in Hall B. Additionally, preliminary cost estimates for the gas
system and controls have been attached.
Regards,
--
Marc McMullen
Detector Support Group
757-269-7738
_______________________________________________
Dsg-mvt mailing list
Dsg-mvt at jlab.org
https://mailman.jlab.org/mailman/listinfo/dsg-mvt
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_ft/attachments/20170426/ab4df1db/attachment-0002.html>
More information about the Dsg-ft
mailing list