[Dsg-ft] FT installation

Raffaella De Vita Raffaella.Devita at ge.infn.it
Wed Jul 5 11:28:49 EDT 2017


Hi Amanda,
apologies for not alerting you before. Cables were indeed disconnected 
yesterday to prepare for the installation that will take place this 
week. I believe the calorimeter will be moved to the Hall tomorrow and 
mounted the next days. The rest will follow.
Marco is onsite and is coordinating the effort.
Regards,
     Raffaella

Amanda Hoebel wrote:
> Hi Raffaella,
>
> For clarification to the last email, we were wanting to know the schedule of the FT because we noticed the humidity sensors we had been monitoring were disconnected and saw some collaborators working on the detector.
>
> Regards,
> Amanda